Case Study 3
 


Pottery Barn Kids
7000 sq. foot Cyprus pre-finished hardwood floor.

"I thought I’d send you pictures of our latest job to give you an idea of what drying with heat is all about.  I can’t even imagine how many applications TES could have in your business."

Wednesday
Sprinklers flooded store 8:30 p.m.
Extracted water for 4 hours

Thursday
Took readings (both hardwoods and ¾ plywood subfloor affected)
Setup injectidry system with mats
Tented floor
Started TES at 3:00 p.m.

Friday
8:00 a.m. (took readings)
     Hardwood floor - DRY!!
     Subfloor made substantial progress
3:00 p.m. met with contractor
     Hardwood and Subfloor DRY in 24 hours.

Saturday
Picked up TES

Saturday-Sunday
Contractor Sanded and refinished floor.

Monday
Store Contractor Scheduled to deliver and install fixtures.

A job that would have taken conventional drying equipment 7 to 9 days was done in less than 48 hours.  All that was left was to bill the customer... $20,000!!

"If you have any interest in having me do a TES demo on one
of your jobs, please call me and we can discuss making arrangements."

Dean Philips or Chris Belt