|
Arrived at the Job: 2-21-08 at 1:00pm.
Cause of the Loss: Malfunction of toilet tank valve.
Affected Areas: Kitchen Ceiling, 2nd Floor Bathroom, Hallway, 2Bedrooms and Small area in Dining room Ceiling.
Upstairs:
Hallway from Bathroom to Stairs, Approx. 4 ft x 12ft in bedroom to left and approx 6 ft into the room running back to corner of where the closet starts. Mostly affected was sub floor and carpet and carpet padding. The cabinets in the bathroom were affected slightly about 3 -4" up from the floor.
Downstairs:
Kitchen ceiling was almost completely affected to end of bar, 2 seams in sheetrock were affected and the common wall between the kitchen and the dining room. Dining Room: Where the ceiling and the wall meet there were approx. 6 small spots that showed up during inspection. None of the water had affected the actual walls; most of the water was contained into the ceiling.
Drying Procedures:
We decided to use a heated drying system on the structure (TES – thermal energy system). We install 2 Tex boxes with air movers upstairs with and exhaust control unit in the bath room. We installed 2 Tex boxes with airmovers, exhaust control unit in the kitchen and dining areas. We zipped walled off the affected areas to direct the heated air directly to the affected areas. (As recommended in the I.I.C.R.C. S500)
This was done after a sub surface extraction was performed on the upstairs affected areas with a truck mounted extraction unit and a water claw.
02/21/08 – 8:00pm (START TIME)
Checked the drying areas and units to ensure all areas were being heated and took data readings for benchmark readings.
02/22/08 – 8:30am (12 ˝ HOURS INTO THE DRY TIME)
Took data readings from affected areas, some drying had taken place but areas were not dry. Continued the drying process.
02/22/08 – 6:30 pm (22 ˝ HOURS INTO THE DRYING TIME)
Took data readings in the affected areas, most of the jobs was almost dry. We re-adjusted our equipment to better dry the job and changed out the propane tanks on the TES unit. Job should be dry between 10 – noon tomorrow.
2/23/08 – 8:00am (36 hours into the drying time)
Took data readings and checked the drying areas to ensure all areas were dried and this confirmed the structure was completely dry.
Customer was very impressed that we were done with the drying process in less than 40 hours. |